Guide

Inspection vs cleaning: why NFPA separates them

Updated 2026-09-16

Operators often treat the hood sticker calendar as proof the system was cleaned. Secondary NFPA 96 explainers say the standard deliberately splits the work: an inspection cadence (how often someone measures grease) and a cleaning trigger (how much grease forces a clean). Those are different events, different reports, and sometimes different visit outcomes — especially in moderate- and low-volume kitchens. Section numbers and thresholds below are secondary summaries. Buy or cite the edition your AHJ adopted; this is not the official text and not legal advice.

Short answer Secondary 2024-edition explainers describe Table 12.4 as an inspection schedule (solid monthly / high quarterly / moderate semiannual / low annual), not a cleaning schedule. Cleaning is required under the secondary §12.6 framing when measured grease crosses the applicable depth threshold (often summarized as ~0.002 in on hoods/filters/fans/ducts, ~0.078 in on other surfaces, ~0.125 in in fan housings). High-volume and solid-fuel kitchens usually clean at nearly every inspection; lower-volume kitchens may inspect without cleaning some cycles — still need the written inspection report and label.

Two jobs, two clocks

JobWhat it is (secondary)What sets the timingTypical paper trail
InspectionTrained/qualified/certified person (acceptable to the AHJ) measures grease buildup across the exhaust pathTable 12.4 by cooking tier / fuelHood label + written inspection report within ~2 weeks (secondary §12.6.13 / §12.6.14)
CleaningContaminated portions cleaned when inspection finds deposits past the applicable threshold (and “before heavily contaminated” intent)Measured depth / contamination finding — not the calendar aloneHood label + access-panel tags + written cleaning report within ~2 weeks (secondary §12.6.10 / §12.6.15)

Same visit can include both. That is common on solid-fuel and high-volume lines. It is not automatic on every Table 12.4 date for every kitchen.

Inspection cadence (secondary Table 12.4)

Cooking tier (secondary)InspectExamples secondary sources listPractical cleaning reality
Solid fuelMonthlyWood-fire pizza, BBQ, charcoalPlan a clean nearly every cycle — grease + creosote load fast
High volumeQuarterly24-hour cooking, charbroil, wokUsually clean at the same visit — paper-thin film on ducts/hoods trips easily
Moderate volumeSemiannualTypical sit-down restaurantsInspect on schedule; clean when depths trip
Low volumeAnnualChurch, seasonal, senior / day-camp style kitchensMay pass without a clean some years — still need the written inspection file

Misclassification is the common operator trap: a “casual” menu with a long charbroil day is often operationally high-volume for grease load. Pair with the volume planners linked below.

Cleaning trigger (secondary §12.6.1.1)

Field note — sticker ≠ cleaned

Operator habits that hold up

  • Ask every visit: inspection only, cleaning, or both?
  • Require the depth reading (or comb photo) and which surface threshold applied
  • File inspection report and cleaning report as separate tabs when both exist
  • Budget combined visits for solid-fuel / high-volume; budget inspection-first for moderate / low
  • Match scope to the full path: hood → filters → plenum → ducts → fan → containment

Common mix-ups

  • “We’re on a quarterly sticker — we’re cleaned quarterly” (not always)
  • Treating Table 12.4 as a fixed cleaning calendar for every kitchen
  • Accepting “all good” with no inaccessible-area callouts
  • Using “1/8 inch everywhere” as the only cleaning rule (fan-housing shorthand)
  • Skipping the written report because the sticker looks fresh

Who it’s for / not for

Sources