Grease ducts run hot in a fire. Code keeps wood, paper stock, and other combustibles a measured distance from hoods, filters, fans, and ducts — or requires a listed enclosure / wrap that permits a shorter distance. Managers do not redesign clearances, but they do catch storage shoved against a duct, wrap torn at an access door, and “temporary” plywood left after a remodel. This page is the operator view of those rules.

Short answer Secondary NFPA 96 §4.2.1: where enclosures are not required, hoods, grease-removal devices, exhaust fans, and ducts need at least 18 in (457 mm) to combustible material, 3 in (76 mm) to limited-combustible material, and 0 in to noncombustible material — unless the component is listed for a lesser clearance. Clearance can be reduced with code-described sheet-metal / insulation assemblies or a listed field-applied grease duct enclosure evaluated to ASTM E2336 (clearance then follows the listing, including zero-clearance products). Shaft or wrap enclosures are a separate construction path; access doors must stay usable. See fire wrap — what a cleaner can and can’t touch. Your AHJ’s adopted edition wins.

Default clearances (no enclosure required)

Adjacent materialMinimum clearance (secondary §4.2.1)Manager check
Combustible (wood framing, cardboard, paper goods, many plastics)18 in (457 mm)No storage, pallets, or temp walls against bare duct / hood sides
Limited-combustible3 in (76 mm)Confirm the material is actually limited-combustible — do not guess
Noncombustible0 inStill keep access panels clear of clutter
Listed hood / duct / device with reduced clearancePer listingKeep the listing sheet; installers follow the label, not a verbal “it’s fine”

How clearance gets reduced (secondary §4.2.3)

MethodWhat secondary text allowsManager note
28-gauge sheet metal on 1 in noncombustible spacersDown to 9 in to combustiblesField-built; not the same as a listed wrap system
22-gauge sheet metal on 1 in mineral wool / ceramic fiber with mesh, on 1 in spacersDown to 3 in to combustiblesSame — construction detail, not kitchen-staff work
Listed field-applied grease duct enclosure (ASTM E2336)Clearance per the listing (often zero)Continuous coverage; damaged wrap is a repair job, not a cleaner improvisation
Listed factory-built grease duct enclosurePer listingSame continuity and firestop rules at penetrations

Partial wrap applied only to “shave” clearance at one tight spot is a common red flag in mechanical-code commentary — enclosure systems are meant to run continuous, with listed firestops where the duct penetrates rated construction. Confirm with your AHJ / design professional before accepting a patch job.

What managers should flag on a walk-through

A grease fire that finds a breach into a combustible ceiling is how small cookline events become structure losses. See fire incident case studies.

Who calls whom

FindingWhoNot
Storage too close to duct / hoodKitchen / facilities — move it nowWaiting for the next hood clean
Damaged wrap, missing enclosure, questionable clearance reductionMechanical / fire-protection contractor + AHJ as requiredHood cleaner “patching” with leftover blanket
Access door that no longer opens or is buriedSheet metal / GC; cleaner documents inaccessible areasSkipping that duct section indefinitely
New hood or relocated ductDesign professional + plan reviewManager measuring with a tape and calling it code

Who it’s for / not for